3P、4P、6P電軌配有弧度時,必須採用橫向安裝。
When the 3P, 4P, and 6P electric tracks have cambers, the lateral installation must be adopted.
在轉彎處起點開始算,每0.5m配一只電軌夾。
The hanger clamp are installed every 0.5 meter from the starting point of the turning.
3P、4P、6P電軌拉緊器架設,必須比電軌夾高約5m/m以防水順電軌而下至電源處,造成短路現象。
The 3P, 4P, and 6P strainer for electric tracks must be installed at the place which is about 5m/m higher than the hanger clamp. It can prevent the water to flow to the power-source place along the electric track; hence the short circuit won’t occur.
3P、4P、6P電軌不適用於室外或酸鹼成分高之場所。
The 3P, 4P, and 6P electric tracks are not suitable for use in outdoor or the place with high acid/alkali contents.
拉緊器與電軌接合處應塗上矽膠。
The silica gel must be coated on the joint place of the strainer and the electric track.